Installer Team Leader - job description
I. Installation of clean room panels
• Scaling positions for placing panels with a laser meter according to the blueprint and plan given by the design team-according to the project (knowledge of reading project drawings).
• Placement of guides and U-profiles according to the drawn positions (base for the panel)
• Placing the panel:
o Smaller panel 3x1.2m weighing up to 75kg
o Larger panels up to 12m high - lifting by robotic arm and vacuum
The panels are screwed into each other.
• Installation of hangers and L-profiles for the ceiling; screws into the panel
• Hanging the ceiling, screwing and fixing it to make it as strong as possible
• Placing and screwing the holker into the ceiling and floor to close all voids and ensure solidity
• Installation of double-glazed windows
• Installing the door:
o Rolling doors
o Slide
o Regular
• Cutting holes for sockets and switches according to the project
• Siliconization of all joints and all elements
II. Installation of HVAC systems
• Creating channels for air flow
o Polyurethane styrofoam pieces are cut according to the blueprint and sorted
o Gluing the parts to form a channel
o PT3 tape is glued to the cones
o The flanges for connecting the ducts are tapped
o Siliconization of all joints
• The finished channel is placed on the ceiling
• Connection of HVAC units
• Screwing, installation of sealing tape and siliconization
• Each chamber has its own damper/valve to which the channel is attached:
o Sponge tape and silicone
• Installation of housing and HEPA filter
III. Ability
• Troubleshooting installation issues
• Changes in the project
• Alignment with the acquired state of the object
IV. Team management
• Manages a team of 3-5 installers
• Makes sure the team has the equipment to work
• Makes sure that there is enough material to work with
• Controls the quality of works
• Introduces the new employee to the job
• Takes care of safety at work
Tool handling:
1. Screwdriver
2. Sander
3. Hammer
4. Parakeets-pincers
5. Burgia
6. Tools for cutting aluminum
Operation of machines:
1. Forklift
2. Robotic arm
3. Lifting platform and equipment for working at height
Permit to work at height
Good communication
Ability to organize work and people
Ability to manage time
The ability to develop and raise the knowledge of employees in the team